It costs you 12 to draw a sample of size n = 1 and measure the attribute of interes...
Check the final answer first, then review the worked steps.
Check the final answer first, then review the worked steps.
a. E = 2.5; n = (1.96 15 / 2.5)^2 = 138.3 -> 139. Cost = 139 12 = 1668 <= 2000. b. 90% z = 1.645; n = (1.645 15 / 2.5)^2 = 97.4 -> 98. Cost = 98 12 = 1176 <= 2000.