Using the high-low method, unit variable overhead cost is calculated to be: 1.80.,...

Check the final answer first, then review the worked steps.

Answer

\($1.50.\)

Work

High: (2,870, $9,130); Low: (2,070, $7,930)
\frac{9,130 - 7,930}{2,870 - 2,070} = \frac{1,200}{800} = 1.50

Step-by-step solution

  1. Identify the high and low activity levels (machine hours) from the table: High is 2,870 (May) and Low is 2,070 (June).
  2. Find the corresponding total overhead costs for these levels: High cost is $9,130 and Low cost is $7,930.
  3. Calculate the change in cost and the change in hours: $\Delta \text{Cost} = 9,130 - 7,930 = 1,200$ and $\Delta \text{Hours} = 2,870 - 2,070 = 800$.
  4. Calculate the variable cost per unit (machine hour) by dividing the change in cost by the change in hours: $\frac{1,200}{800} = 1.50$.