Using the high-low method, total monthly fixed overhead cost is calculated to be:
Check the final answer first, then review the worked steps.
Check the final answer first, then review the worked steps.
High: (2,100, $6,620); Low: (1,600, $5,590)
Variable cost = (6,620 - 5,590) / (2,100 - 1,600) = 1,030 / 500 = $2.06/hr
Fixed cost = 6,620 - (2.06 * 2,100) = 6,620 - 4,326 = $2,294