If Soren Industries expects that the manufacturing time and learning rate will be t...

Check the final answer first, then review the worked steps.

Answer

7873

Work

T_1 = 750, LR = 0.90, n = 16
b = \frac{\log(0.90)}{\log(2)} \approx -0.152003
Cumulative Average Time = 750 \times 16^{-0.152003} = 492.075
Total Hours = 16 \times 492.075 = 7873.2 \approx 7873

Step-by-step solution

  1. Identify the learning rate $LR = 0.90$ and the time for the first unit $T_1 = 750$ hours.
  2. Use the learning curve formula for cumulative time: $T_n = T_1 \times n^b$, where $b = \frac{\log(LR)}{\log(2)}$.
  3. Calculate the learning index $b = \frac{\log(0.90)}{\log(2)} \approx -0.152003$.
  4. Calculate the cumulative time for 16 units: $T_{16} = 750 \times 16^{-0.152003} \approx 750 \times 0.6561 = 492.075$ hours per unit on average.
  5. Calculate total hours for 16 units: $16 \times 492.075 = 7873.2$ hours.
  6. Round to the nearest whole number: $7873$.