Crimson Company produced a pilot run of 50 units with 0.55 direct labor hours per u...

Check the final answer first, then review the worked steps.

Answer

0.21408.

Work

b = \ln(0.8)/\ln(2) = -0.321928
a = 0.55 / 50^{-0.321928} = 1.610521
Total hours = 1.610521 \times 800^{0.678072} = 171.8656
Average = 171.8656 / 800 = 0.21483

Step-by-step solution

  1. Identify the learning curve model: The cumulative average time for $n$ units is $Y_n = a n^b$, where $a$ is the time for the first unit and $b = \frac{\ln(\text{learning rate})}{\ln(2)}$.
  2. Find $a$: For the first 50 units, the average time is 0.55 hours. So, $0.55 = a(50)^b$. With an 80% learning rate, $b = \frac{\ln(0.8)}{\ln(2)} \approx -0.321928$. Thus, $a = \frac{0.55}{50^{-0.321928}} \approx 0.55 \times 2.92822 \approx 1.61052$.
  3. Calculate total hours for 800 units: The total time for $n$ units is $n \times Y_n = a n^{1+b}$. For $n=800$, total hours $= 1.61052 \times 800^{1-0.321928} = 1.61052 \times 800^{0.678072} \approx 1.61052 \times 74.4256 \approx 171.865$.
  4. Calculate average time: Divide total hours by 800: $\frac{171.865}{800} \approx 0.21483$. Re-evaluating with higher precision: $a = 0.55 \times 50^{0.321928} = 1.610521$. Total hours $= 1.610521 \times 800^{0.678072} = 171.8656$. Average $= 171.8656 / 800 = 0.21483$. Checking the provided options, 0.21408 is the closest match.