At 400 hours of activity, Nailor management can be approximately two-thirds confide...

Check the final answer first, then review the worked steps.

Answer

\(3,520.26 to 3,679.76.\)

Work

$a = 656.57, b = 7.3586, S_{e} = 79.75, X = 400 \\ \hat{Y} = 656.57 + 7.3586(400) = 3600 \\ \text{Range} = 3600 \pm 79.75 = [3520.25, 3679.75]

Step-by-step solution

  1. Identify the regression equation: $Y = a + bX$, where $a = 656.57$ and $b = 7.3586$.
  2. Calculate the predicted cost at $X = 400$ hours: $\hat{Y} = 656.57 + 7.3586(400) = 656.57 + 2943.44 = 3600$.
  3. Determine the confidence interval: A two-thirds confidence level corresponds to $\pm 1$ standard error of the estimate ($S_{e} = 79.75$).
  4. Calculate the range: $3600 \pm 79.75$, which gives $3520.25$ to $3679.75$. This matches the option $3520.26$ to $3679.76$ (allowing for minor rounding differences).